At the July 15 City Council meeting, OHM Advisors’ team of John Katers, engineer, and Stacy Tober, landscape
architect, presented an update on the roundabout slated for 7 Mile and
Sheldon Road, including proposed landscaping, cross-walks, costs and
scheduling. The roundabout is estimated to cost $2.55 million with $2.17
million in federal grants and a grant match of $375,000 to be paid by
the city. The proposed timeline is to begin construction in July 2025
and complete it in three months. View the
slide deck here.